Second Lift Hill Complete
Saturday 20th April 2013

Work around the smiler site has progressed nicely over the past few weeks. With more track installed and the station and maintenance building both completely waterproof now. Yellow piping has been added to the front of the station building. From track painting to installing sections of the first lift hill the site was a hive of activity today. However, installing one section of track just after the second lift hill seemed to have an issue.